News

Contracta terminates appointments of 1,500 workers in Kumasi

 About 1,500 workers em­ployed for the construction of the Kumasi Central Mar­ket, Kumasi International Airport and the Komfo Anokye Teaching Hospital’s Mother and Baby Unit (MBU) have had their appoint­ments terminated by their employ­ers, Contracta of Brazil.

The development commenced in December 2022 when work stalled at the three construction sites.

From December 2022, the firm started the termination of ap­pointment on monthly batches, in accordance with the Labour Act, that affected 1,500 staff.

Otumfuo Osei Tutu II, Asante­hene, who facilitated a loan for the project, is reported to have been informed of the development.

A management member of the company, speaking on condi­tion of anonymity, disclosed to some selected journalists that all the affected staff were given one month’s notice of termination of appointment followed by compen­sation package.

“Management didn’t want to violate the country’s labour laws so we followed every step includ­ing medical check out. This is not something we intended to do but the situation forced us to do that,” the source said,

He disclosed that the Kumasi Airport phase 2 projects, which was about 95 per cent complet­ed, and left with the installation of gadgets, control towers, and extension of runways and demol­ishing of existing structures, were on hold due to lack of funds to facilitate the completion of the entire project.

He explained that “the project has been affected by the ongoing government debt restructure pro­gramme. Government, I mean the Finance Minister has suspended external payment”.

So the UK government respon­sible for funding the project, has stopped releasing funding to us to work on the project. We are ready to work but we don’t have money to pay workers and buy materials, so that’s the problem we are facing at the moment…so the Asantehene, who facilitated the loan through Prince Charles, has been put in the known of the situation to do something about it,” the source claimed.

The sod-cutting for the Central Market project was held on May 2, 2019 by President Nana Addo Dankwa Akufo-Addo, in the com­pany of the Asantehene, and was scheduled to be completed by the end of March 2024.

“We can’t meet the deadline for the traders to come and trade in the Central Market. This is because the former Kumasi Metropolitan Chief Executive failed to relocate the traders on time for the project to start as we wanted,” the source added.

Another source also confirmed to the Ghanaian Times that Asante­hene, Otumfuo Osei Tutu II, had been briefed on the situation at the three sites due to the funding challenges.

FROM KINGSLEY E.HOPE, KUMASI#

Show More
Back to top button